FY 2024 - Project Name/Phase:  Hedge Street Phase 4 Construction
Project/Location: Construction of Phase 4 Streetscape improvements on Hedge Street from 70 Hedge Street to Adams Street.  

Status:  The Town is applying for CDBG funds to complete the final phase of work along Hedge Street including sidewalk, water, sewer and drainage repairs.

Letters of Support:  We also appreciate receiving letters of support that we will submit with the grant application.  Here is a template you can use.  Please email your letters to Paul DiGiuseppe

Next Public Meeting

Select Board Meeting Public Hearing to approve application:  February 26, 2024

CDBG Grant Application Deadline: March 25,2024 
CDBG Grant Request:  $919,626

Proposed Plans

Engineers Report

Video Discussing the Proposal 

Questions or comments about the proposal?  Please direct all inquiries to Paul DiGiuseppe at 508-979-4023 x 8122


FY 2021 - Project Name/Phase:  Hedge Street Phase 3 Construction
Project/Location: Construction of Phase 3 Streetscape improvements on Hedge Street between Main Street and halfway to Adams Street.
Dates: February 2022 - January 2023
CDBG Funds: $686,283

Project Documents Here

Status:  Completed!


2020 - Project Name/Phase:  Hedge Street Phase 3 Design
Project/Location: Design Engineering of Phase 3 Streetscape improvements on Hedge Street between Main Street and Adams Street.